| Variances by Cruise Ships |
Cruise Ship:  
Amadea 
Cruise Line:  
Bernhard Schulte Cruise Services GmbH & Co. KG 
|
 
VSP Operations Manual Section:  5.3.2.1.1
|
Manual Requirement:
Ensure potable water tanks do not share a common wall with the hull of the vessel or with tanks or piping containing nonpotable water or other liquids.
|
Request: Operate with potable water tanks that share a wall with the vessel hull based on the use of salinity sensors, alarms, a monitoring plan and a contingency plan if leaks are detected.
|
Status:
Approved
|
Summary:Operate with potable water tanks that share a wall with the vessel hull based on the use of salinity sensors, alarms, a monitoring plan and a contingency plan if leaks are detected.
|
|
|
|
|
|